Building work has started on an artificial intelligence data centre near Casablanca that could eventually draw 180 megawatts of power, five times the size first announced, according to the company behind it.
Christopher Yoshida, co-founder and chairman of Nexus Core Systems, said in a LinkedIn post that the campus in Nouaceur was “officially under construction”.
A first 20MW phase is due to open in the third quarter of 2027, with the site reaching 180MW by 2028.
The progress on site rests, for now, on the company’s own statement.
The project is far larger than the deal signed in April at the GITEX Africa tech fair in Marrakech.
That agreement, with Morocco’s digital transition and investment ministries, set out MAD 12bn ($1.2bn) of investment for 36MW of capacity by 2027, in two phases.
The first, in Nouaceur, was to cost MAD 5bn ($500m) for 16MW and create 50 skilled jobs. A second site in northern Morocco would add 20MW for MAD 7bn ($700m), taking direct jobs to 125.
The company now presents Nouaceur as the first part of a 500MW national platform that could grow to 2.1 gigawatts depending on demand.
It has not said how the larger plan fits with the April deal, or updated its figures for investment, financing and jobs.
Megawatts measure how much electricity a data centre uses, not how much computing it can do.
The site is designed for Nvidia’s next generation of chips. UK firm FiveNines Group, which is overseeing construction, has said it will host Nvidia Vera Rubin NVL72 systems, cooled by liquid rather than air because they run so hot.
Nexus plans to rent out computing power to companies, research bodies and governments, and to host their equipment. It says customers will keep control over where their data and AI models are processed, and aims to serve clients in Europe, Africa, the Middle East and North America.
Power is due to come from wind, through a partnership with Taqa Morocco, part of Abu Dhabi energy group Taqa. The volumes and length of the supply deal have not been disclosed.
Running flat out all year, a 180MW site would use more than 1.5 terawatt hours of electricity.
Nexus lists Nvidia, FiveNines and substation builder Fonto Energy among its partners. When the project was announced in April, it was also linked to South Korea’s Naver Cloud and the finance firm Lloyds Capital.
How responsibilities and funding are shared between them has not been made public.
If completed, the campus would dwarf Morocco’s existing data centres. A report by BMI, part of Fitch Solutions, counted 14 facilities with just 1.5MW of operational capacity in the second quarter of 2026.
The government wants to change that. In January it unveiled a “Morocco AI 2030” roadmap, building on its Digital Morocco 2030 strategy, which together aim to create about 240,000 digital jobs and add roughly MAD 100bn ($10bn) to the economy by 2030.